Project Complete.  This project will install and relocate new roof drain lines to the exterior of the building; add structural foundation helical piles; and repair interior finishes to restore the building to pre-Hurricane Harvey condition.

Architect: Collaborate 

Contractor: Kellogg, Brown & Root 

Construction Budget: $811,000.00 

Current Phase: Construction 

Schedule: Start Design February 2020. Start Construction June 2020. Substantial Completion late November 2020.